PROJECT No. |
CUSTOMER / LOCATION |
DESCRIPTION |
MAN HOURS |
YEAR - MONTH |
GALLERY |
26 |
15152 |
Bapco - Bahrain |
Clay filter (16V1616)Fuller’s earth clay replacement works at Bapco-KMU |
3,500 |
April-16 |
|
27 |
15141 |
Bapco - Bahrain |
Carbon Filter(62C6261 AX) activated carbon change out works at Bapco-2 HDU DEA |
2,500 |
April-16 |
|
28 |
15149 |
Bapco - Bahrain |
Catalyst Vacuuming works for FCCU at Bapco during shutdown |
3,500 |
March-16 |
|
29 |
15001 |
SASREF - |
T-8253-Wet slops oil tank (Dia 12.19m, Height 9.14m), blinding, oil vacuuming, open manway, Desludging, hydro jetting, weld build up, patch works, box up, Despading |
3,500 |
March-16 |
|
30 |
11163 |
SASREF - |
T-8140 (Auto Diesel) (Dia 34.14m, Height 16.46m), Blinding, open manway,Desludging, Hydro jetting works, mechanical maintenance, bottom plate (100%) replacement,Annular plate (100%)replacement, Tank hydro testing, box up, Despading |
15,000 |
Jan-16 |
|
31 |
15104 |
Al Muzain - Sipchem |
Shutdown services-Supplied skilled resources and construction equipments for Shutdown at Sipchem |
8,000 |
Nov-15 |
|
32 |
15099 |
Arabian Chemical Terminals - Jubail |
Tank (T-07) Light gas oil) cleaning works-open roof nozzles, butter washing with degreaser (5% soda ash), water flushing, Pipe line flushing |
2,500 |
Oct-15 |
|
33 |
15095 |
Arabian Chemical Terminals - Jubail |
ISO tanks (8 no’s 24 m3)with product (75%PC 32 & 25% Razeen) preheating and dumping at Beeah |
2,500 |
Oct-15 |
|
34 |
15104 |
Al Muzain - Saudi Chevron |
Shutdown services –Supplied skilled resources and construction equipments for Shutdown at Saudi Chevron |
8,000 |
Oct-15 |
|
35 |
15095 |
Arabian Chemical Terminals - Jubail |
Tank (T-112) (Dia5.8m, H-10.7m)—Loading of 120 MT of product (75% PC 32 & 25% Razeen) to ISO containers& disposal @ Beeah, High pressure water jetting of tank floor and butter washing of shell, inspection & box up |
8,500 |
Oct-15 |
|
36 |
15001 |
SASREF - |
Tank T 8208 Diesel tank, Blinding,open manway, Desludging, hydro jetting, inspection,roof repairs, staircase repairs, box up, Despading |
4,500 |
Sept-15 |
|
37 |
11163 |
SASREF - |
T-8214-Dual purpose kerosene (dia 60.96m, height 21.95 mt, Floating roof tank),blinding, open manway, Desludging, hydro jetting, mechanical maintenance, secondary seal replacement, roof plate / bottom plate repairs, box up manway, Despading |
8,500 |
Sept-15 |
|
38 |
15097 |
Arabian Chemical Terminals - Jubail |
Tank (T-116) (Dia 5.8m, Height 10.7mt) (Product—RV 100, 2Ethylexyl nitrate), open top nozzles, Butter washing with degreaser (5% soda ash), vacuum out waste effluents, open side manway, inspection, box up |
3,500 |
Sept-15 |
|
39 |
15096 |
Arabian Chemical Terminals - Jubail |
Tank (T-10) (Dia-12.56m, height 17.0m) (De-aromatized Hydro carbons) tank cleaning-butter washing with 5% soda ash, line flushing with degreaser (5% soda ash), vacuuming, inspection, final box up |
4,500 |
Sept-15 |
|
40 |
11-163 |
Sasref - Jubail |
Crude oil Tank (8102) (60.96mt.H-20.15m)isolation, Desludging, HP jetting, remove and install secondary & primary roof seals, floor patch works (9 no’s), annular plate weld build up, Bleeder vent replacement, Pontoon strip lining repairs, box up |
15,000 |
June-15 |
|
41 |
15-042 |
Nabors - Hawtah Rig#210 |
Hydrojetting works for Rig mast, Derrick & sub structure at Nabors Rig 210-Hawtah |
2,705 |
May-2015 |
|
42 |
15-005 |
SADARA-SASREF - |
CEN Line decommissioning works: 24†& 20†Carbon steel pipe line product drain out, water circulation and handover for tie in operation. Reinstate the line after hot works. Tank product transfer and bolt torquing works. |
8,500 |
May-15 |
|
43 |
11-163 |
Sasref - Jubail |
Liquid Sulfur Tank (5103) ( 10.67 mt. H-12.19 m) isolation, breaking solid sulphur by jack hammer and vacuuming, HP jetting, sketch plate (6 no’s) replacement, Nozzle modifications, sump pit replacement, heating coil removal, new heating coil fabrication (600 inch dia), installation, NDT, Hydro test, painting, box up |
12,000 |
May-15 |
|
44 |
14-185 |
Bapco - Bahrain |
Catalyst vacuuming works for FCC Unit during FCCU STR INT SD-2015 |
8,500 |
May-15 |
|
45 |
14-024 |
GIPC - Bahrain |
Catalyst Replacement works for HT shift converter (R-0401-61.82 m3) and LT shift converter (R-0402-87.7 m3) during GPIC Mar-15 T & 1 |
12,000 |
Apr-15 |
|
46 |
14-027 |
GPIC - Bahrain |
Unloading and reloading of Rasching Rings for CO2 Absorber C0502 (bottom bed 112 m3) during GPIC March-15 T&I |
7,500 |
Apr-15 |
|
47 |
14-051 |
MCSC-GPIC - Bahrain |
Mechanical cleaning by using pneumatic cleaning machine with brushes (SS, Brass, Nylon) of heat exchanger tubes (E0301-565 tubes,dia-29.5 mm; E0301 B-622 Tubes, dia 24.3 mm; E-1201-567 tubes, dia 28.7 mm; E-8301 A 983 tubes, dia 33.88 mm; E-8401 727 tubes, dia 33.9 mm and air blowing for conducting IRIS test |
5,500 |
March-15 |
|
48 |
15-014 |
Bapco - Bahrain |
Catalyst handling works for #Absorbers 58C8802/03/04- KGSP 2015 T&I @ Bapco |
11,500 |
Feb-15 |
|
49 |
11-163 |
SASREF - Jubail |
We slops Tank(8255) ( 12.19 mt. H-9.14 m) isolation, Desludging, HP jetting, roof ladder repairs, heating coil repairs, coil hydro test, box up |
7,500 |
Jan-15 |
|
50 |
14-141 |
DRIC-A1 Tuwairqi - Dammam |
Module-1 (Midrex design) Reformer catalyst change out; Mechanical works, Catalyst unloading (324 tubes), segregation/ pre socking, Catalyst sock loading, DP measurements, Box up |
25,000 |
Jan-15 |
|